Budgeting & Forecasting › Variance Analysis

How do you reconcile standard cost of actual production to actual cost?

Advanced

Answer

Start with the standard cost of actual output, then add adverse and subtract favorable cost variances (materials price/usage, labour rate/efficiency, overhead variances) to arrive at the actual cost. This reconciliation shows how each variance bridges the expected (standard) cost to what was actually incurred.
Std cost of output 100k +/- variances = Actual cost 106k.
Real-world example The reconciliation itemizes how usage and rate variances explain the gap to actual cost.

Common follow-ups: What is the starting point? | What does the reconciliation show?